- Home
- Case Studies
- [fi_FI] Jæren Everk chooses our cable pusher to save time and costs
[fi_FI] Jæren Everk chooses our cable pusher to save time and costs
[fi_FI]
When Jæren Everk faced a demanding 1100 meter cable run, they chose to test a new method to avoid digging up the asphalt walkway.
Using Melbye's cable pusher, the team completed the run in a fraction of the expected time, saving both cost and disruption for the local community.
ArticlesRelated articles
[fi_FI] Energy Storage for Commercial Buildings
[fi_FI] Flexible foundation solutions helped accelerate the deployment of solar and battery storage systems while reducing installation complexity and project risk.
Read More arrow_right_alt[fi_FI] Fire-rated optotubes and microtubes for safe indoor installations
[fi_FI] In tunnels, hospitals, airports and other public environments, it is often the details behind the walls that determine how safe a building actually is in the event of a fire.
Read More arrow_right_alt[fi_FI] The next generation of engineers on the road
[fi_FI] When technology students build a solar car that will drive 3,000 kilometers through the Australian desert.
Read More arrow_right_altNeed help finding the right product?
Our experts are here to help you find the right solution for your project. Get in touch for product advice, support or a quote.
Get In Touch arrow_right_alt
Danish
Swedish
Norwegian
Finnish
English
![[fi_FI] Energy Storage for Commercial Buildings](/WEB/CaseStudies/case-futureCase.png)
![[fi_FI] Fire-rated optotubes and microtubes for safe indoor installations](/WEB/CaseStudies/blogs-b1.png)
![[fi_FI] The next generation of engineers on the road](/WEB/CaseStudies/blogs-b2.png)